1
Items 59 and 60 — DEAD STOCK TAKEN OVER, AND THE EARNINGS USEDमद 59 और 60 — लिया गया निष्क्रिय स्टॉक, और आय का उपयोग
Item 59 takes over the dead stock of an existing PRIVATE catering unit into a departmental catering unit.
  • PHOD: full power up to RS 30,000
  • That figure is for each catering unit, or each group of units, proposed to be taken over for departmental work
  • Finance concurrence is NOT required
  • ITEM 60 — THE EARNINGS OF A DEPARTMENTAL ESTABLISHMENT
    • The PHOD may authorise the utilisation of those earnings
    • They defray the day to day expenses connected with running such an establishment
    • Those expenses are the purchase of perishable items, vegetables, fish, meat and eggs
    • DRM: FULL POWER
    • Finance concurrence is not required
    So the kitchen may spend what it earns on what spoils, and you should name the items it may buy.
मद 59 मौजूदा निजी खानपान इकाई का निष्क्रिय स्टॉक विभागीय खानपान इकाई में लेती है।
  • पीएचओडी: 30,000 रुपये तक पूर्ण शक्ति
  • वह आँकड़ा हर खानपान इकाई, या इकाइयों के हर समूह के लिए है, जिसे विभागीय काम के लिए लेना प्रस्तावित हो
  • वित्त सहमति आवश्यक नहीं
  • मद 60 — विभागीय प्रतिष्ठान की आय
    • पीएचओडी उस आय के उपयोग का प्राधिकार दे सकते हैं
    • वह ऐसे प्रतिष्ठान को चलाने से जुड़े दैनिक व्यय पूरे करती है
    • वे व्यय हैं नाशवान मदों, सब्जियों, मछली, मांस और अंडों की खरीद
    • मंडल रेल प्रबंधक: पूर्ण शक्ति
    • वित्त सहमति आवश्यक नहीं
    अर्थात् रसोई जो कमाती है वह उस पर खर्च कर सकती है जो खराब होता है, और वे मदें आप बताइए।
2
Items 61 to 64 — A SPONSOR, CSR AND A NEW PRSमद 61 से 64 — प्रायोजक, सीएसआर और नया पीआरएस
Item 61 permits the execution of works for passenger amenities at railway stations, sponsored from outside.
  • The sponsors are individuals, NGOs, trusts, charitable institutions and corporates
  • DRM: FULL POWER; finance concurrence IS required
  • ITEM 62 — WORK THROUGH CORPORATE SOCIAL RESPONSIBILITY
    • It executes identified railway works through the CSR of corporates and public sector undertakings
    • What is approved is the MASTER PLAN, and the DRM has FULL POWER
    • Sponsoring agencies may include NGOs
    • A DEPOSIT WORK is permitted from CSR funding where the party is unwilling to execute the work itself
    • Investment by the sponsoring agency carries NO LIMIT, the DRM having full power
    • The earlier limit for the DRM was Rs 2 crore
  • ITEMS 63 AND 64
    • Item 63 rents space for opening a PRS at a NON-RAIL HEAD location: DRM FULL POWER
    • Item 64 provides a new UTS or PRS, that is it converts a UTS or PRS into a UTS-CUM-PRS: DRM FULL POWER
    • In both, finance concurrence is necessary
    So the sponsor's investment is no longer capped, and you should name the old Rs 2 crore when you say so.
मद 61 रेल स्टेशनों पर यात्री सुविधाओं के कार्य कराने की अनुमति देती है, जो बाहर से प्रायोजित हों।
  • प्रायोजक हैं व्यक्ति, गैर-सरकारी संगठन, न्यास, धर्मार्थ संस्थाएँ और निगम
  • मंडल रेल प्रबंधक: पूर्ण शक्ति; वित्त सहमति आवश्यक है
  • मद 62 — निगमित सामाजिक उत्तरदायित्व से कार्य
    • यह निगमों और सार्वजनिक उपक्रमों के सीएसआर से चिह्नित रेल कार्य कराती है
    • जो अनुमोदित होता है वह गुरु योजना है, और मंडल रेल प्रबंधक को पूर्ण शक्ति है
    • प्रायोजक एजेंसियों में गैर-सरकारी संगठन भी हो सकते हैं
    • जहाँ पक्षकार स्वयं कार्य कराने को तैयार न हो, वहाँ सीएसआर निधि से जमा कार्य की अनुमति है
    • प्रायोजक एजेंसी के निवेश पर कोई सीमा नहीं, और मंडल रेल प्रबंधक को पूर्ण शक्ति है
    • मंडल रेल प्रबंधक की पहले की सीमा 2 करोड़ रुपये थी
  • मद 63 और 64
    • मद 63 रेल-रहित स्थान पर पीआरएस खोलने के लिए स्थान किराये पर लेती है: मंडल रेल प्रबंधक पूर्ण शक्ति
    • मद 64 नया यूटीएस या पीआरएस देती है, अर्थात् यूटीएस या पीआरएस को यूटीएस-सह-पीआरएस में बदलती है: मंडल रेल प्रबंधक पूर्ण शक्ति
    • दोनों में वित्त सहमति आवश्यक है
    अर्थात् प्रायोजक के निवेश पर अब सीमा नहीं है, और कहते समय पुरानी 2 करोड़ रुपये आप बताइए।
3
Part E Annexure A — THE COMMITTEE FOR AN EARNING CONTRACTभाग E अनुबंध A — आय संविदा की निविदा समिति
The annexure sets the committee and the accepting authority for earning contracts, other than catering and parcel contracts.
  • Up to RS 50 LAKH: a JUNIOR SCALE committee, and the DCM accepts
  • Above Rs 50 lakh up to Rs 5 crore: a SENIOR SCALE committee, and the Sr DCM accepts
  • Above Rs 5 crore up to Rs 10 crore: a JAG committee, and the ADRM accepts
  • Above Rs 10 crore up to Rs 100 crore: a JAG committee again, and the DRM accepts
  • Above RS 100 CRORE: a SAG committee, and the PCCM or CCM accepts
  • In the absence of the PCCM or CHOD, the AGM accepts
  • A Junior Scale committee is a TWO MEMBER committee of Accounts and Commercial officers, unless the rules prescribe otherwise
  • Every other committee is a THREE MEMBER committee of Accounts, Commercial, and one member the competent authority nominates
So the JAG committee serves two bands and the accepting authority tells them apart, and you should read the value first.
यह अनुबंध खानपान और पार्सल से भिन्न आय संविदाओं की समिति और स्वीकार प्राधिकारी तय करता है।
  • 50 लाख रुपये तक: कनिष्ठ श्रेणी की समिति, और स्वीकार डीसीएम करते हैं
  • 50 लाख रुपये से ऊपर 5 करोड़ रुपये तक: वरिष्ठ श्रेणी की समिति, और स्वीकार वरिष्ठ डीसीएम करते हैं
  • 5 करोड़ रुपये से ऊपर 10 करोड़ रुपये तक: जेएजी समिति, और स्वीकार एडीआरएम करते हैं
  • 10 करोड़ रुपये से ऊपर 100 करोड़ रुपये तक: फिर जेएजी समिति, और स्वीकार मंडल रेल प्रबंधक करते हैं
  • 100 करोड़ रुपये से ऊपर: एसएजी समिति, और स्वीकार पीसीसीएम या सीसीएम करते हैं
  • पीसीसीएम या सीएचओडी की अनुपस्थिति में अपर महाप्रबंधक स्वीकार करते हैं
  • कनिष्ठ श्रेणी की समिति लेखा और वाणिज्य अधिकारियों की दो सदस्यीय समिति है, जब तक नियम अन्यथा न कहें
  • शेष हर समिति लेखा, वाणिज्य, और सक्षम प्राधिकारी के नामित एक सदस्य की तीन सदस्यीय समिति है
अर्थात् जेएजी समिति दो खंडों में बैठती है और उन्हें स्वीकार प्राधिकारी अलग करता है, और पहले मूल्य आप पढ़िए।
4
Part E Annexure B — THE COMMITTEE FOR A PARCEL LEASING TENDERभाग E अनुबंध B — पार्सल पट्टे की निविदा की समिति
The second annexure covers parcel leasing tenders, that is the CPLP and the PCET.
  • Up to RS 2.5 CRORE: a Junior Scale committee, and the DCM accepts
  • Above Rs 2.5 crore up to Rs 5 crore: a Senior Scale committee, and the Sr DCM accepts
  • Above Rs 5 crore up to RS 50 CRORE: a JAG committee, and the ADRM accepts
  • Above Rs 50 crore up to Rs 100 crore: a JAG committee, and the DRM accepts
  • Above Rs 100 crore: a SAG committee, and the PCCM or CCM accepts, or the AGM in their absence
  • The bands here start higher than in Annexure A, because a parcel lease is a larger contract
So the two annexures share their committees but not their bands, and you should pick the annexure by the kind of contract.
दूसरा अनुबंध पार्सल पट्टे की निविदाओं को, अर्थात् सीपीएलपी और पीसीईटी को, ढकता है।
  • 2.5 करोड़ रुपये तक: कनिष्ठ श्रेणी की समिति, और स्वीकार डीसीएम करते हैं
  • 2.5 करोड़ रुपये से ऊपर 5 करोड़ रुपये तक: वरिष्ठ श्रेणी की समिति, और स्वीकार वरिष्ठ डीसीएम करते हैं
  • 5 करोड़ रुपये से ऊपर 50 करोड़ रुपये तक: जेएजी समिति, और स्वीकार एडीआरएम करते हैं
  • 50 करोड़ रुपये से ऊपर 100 करोड़ रुपये तक: जेएजी समिति, और स्वीकार मंडल रेल प्रबंधक करते हैं
  • 100 करोड़ रुपये से ऊपर: एसएजी समिति, और स्वीकार पीसीसीएम या सीसीएम, उनकी अनुपस्थिति में अपर महाप्रबंधक करते हैं
  • यहाँ खंड अनुबंध A से ऊँचे शुरू होते हैं, क्योंकि पार्सल का पट्टा बड़ा संविदा है
अर्थात् दोनों अनुबंधों की समितियाँ एक जैसी हैं पर खंड नहीं, और संविदा के प्रकार से अनुबंध आप चुनिए।
Report an error on this pageइस पेज में गलती बताएँ

Finished this page? Practise it now.यह पेज पूरा हुआ? अब इसका अभ्यास कीजिए।

or take the free Mock CBTया फ्री Mock CBT दें