1
Item 14(A) — RE-APPROPRIATION OF REVENUE GRANTSमद 14(A) — राजस्व अनुदानों का पुनर्विनियोग
The item lets the railway move money already voted, and part (A) is the revenue grant.
- PHOD/HOD: FULL POWERS to distribute or redistribute their department's budget between divisions and units
- That move stays under the SAME DEMAND, that is the same sub major head, and the same PU
- It carries the concurrence of the FA&CAO/Budget
- DRM or CWM: FULL POWERS to re-appropriate the budget allotted to the division or unit
- That move stays within the same department, same demand or sub major head, and same PU, BETWEEN SUB-HEADS
- It carries the concurrence of associate finance; ADRM: NIL; divisional officers: NIL
- THE NOTES
- The zonal railways' powers of re-appropriation under revenue grants are communicated by the Railway Board in its letters advising spending units
- By the Board's letter of 23.04.2018 the zonal railways may re-appropriate between PU 27, PU 28 and PU 32
- That was for safety related urgency during 2018-19, is vested with the GM, and needs finance concurrence
- पीएचओडी/एचओडी: अपने विभाग का बजट मंडलों और इकाइयों के बीच बाँटने या फिर बाँटने की पूर्ण शक्तियाँ
- यह हटाव उसी मांग, अर्थात् उसी उप मुख्य शीर्ष, और उसी पीयू में रहता है
- इसके साथ वित्त सलाहकार एवं मुख्य लेखाधिकारी/बजट की सहमति होती है
- मंडल रेल प्रबंधक या सीडब्ल्यूएम: मंडल या इकाई को आवंटित बजट का पुनर्विनियोग करने की पूर्ण शक्तियाँ
- यह हटाव उसी विभाग, उसी मांग या उप मुख्य शीर्ष, और उसी पीयू में, उप शीर्षों के बीच रहता है
- इसके साथ सहयोगी वित्त की सहमति होती है; एडीआरएम: शून्य; मंडल अधिकारी: शून्य
- नोट
- राजस्व अनुदानों में जोनल रेलवे की पुनर्विनियोग शक्तियाँ रेलवे बोर्ड व्यय इकाइयों को भेजे पत्रों में बताता है
- बोर्ड के 23.04.2018 के पत्र से जोनल रेलवे पीयू 27, पीयू 28 और पीयू 32 के बीच पुनर्विनियोग कर सकते हैं
- यह 2018-19 में संरक्षा की अत्यावश्यकता के लिए था, महाप्रबंधक में निहित है, और इसमें वित्त सहमति चाहिए
2
Item 14(B) — LUMPSUM WORKS UNDER DEMAND NO 16मद 14(B) — मांग संख्या 16 के एकमुश्त कार्य
Part (B) moves funds from one work to another under the same plan head and the same source, for lumpsum works.
- PHOD: FULL POWERS to distribute or redistribute the LUMPSUM OUTLAY, that is works costing less than Rs 2.5 crore each
- That is done as per the PINK BOOK for the current financial year, among divisions and units during the year
- It follows the BG, RG or FG, within the same plan head and the same source
- DRM: FULL POWERS to re-appropriate from one sanctioned lumpsum work to another sanctioned lumpsum work of the division or unit
- That is done as per progress or priority, within the same plan head and source
- It must not exceed the total outlay for the year for lumpsum works, as advised by the PLAN HEAD COORDINATOR
- Associate finance's concurrence is required; divisional officers: NIL
- THE NOTES
- The general guidelines in the Board's extant letters are followed
- Outlay for lumpsum works below Rs 2.5 crore for NEW WORKS and for WORKS IN PROGRESS cannot be clubbed
- Those two have to be treated distinctly
- पीएचओडी: एकमुश्त परिव्यय, अर्थात् हर एक 2.5 करोड़ रुपये से कम लागत के कार्य, बाँटने या फिर बाँटने की पूर्ण शक्तियाँ
- यह चालू वित्तीय वर्ष की पिंक बुक के अनुसार, वर्ष में मंडलों और इकाइयों के बीच होता है
- यह बीजी, आरजी या एफजी के अनुसार, उसी योजना शीर्ष और उसी स्रोत में होता है
- मंडल रेल प्रबंधक: एक स्वीकृत एकमुश्त कार्य से मंडल या इकाई के दूसरे स्वीकृत एकमुश्त कार्य में पुनर्विनियोग की पूर्ण शक्तियाँ
- यह प्रगति या प्राथमिकता के अनुसार, उसी योजना शीर्ष और स्रोत में होता है
- यह एकमुश्त कार्यों के लिए वर्ष के कुल परिव्यय से अधिक नहीं होना चाहिए, जैसा योजना शीर्ष समन्वयक बताए
- सहयोगी वित्त की सहमति आवश्यक है; मंडल अधिकारी: शून्य
- नोट
- बोर्ड के प्रचलित पत्रों के सामान्य दिशानिर्देश माने जाते हैं
- 2.5 करोड़ रुपये से कम के एकमुश्त कार्यों में नए कार्य और चालू कार्य का परिव्यय एक साथ नहीं मिलाया जा सकता
- इन दोनों को अलग-अलग मानना होता है
3
Item 14(C) and (D) — WHAT THE ZONE CANNOT MOVEमद 14(C) और (D) — जोन क्या नहीं हटा सकता
The last two parts of item 14 are NIL in every column, and that is their whole teaching.
- (C) From one work to another under the same plan head and same source, for ITEMISED works under Demand No 16
- PHOD: NIL; DRM and SAG: NIL; divisional and headquarters officers: NIL
- It needs the GM's approval with associate finance's concurrence
- The sanction memorandum is generated only through the BUDGET VPN
- (D) From one plan head to another, or from one source of fund to another, for itemised works under Demand No 16
- PHOD: NIL; DRM and SAG: NIL; divisional and headquarters officers: NIL
- It is referred to the RAILWAY BOARD for sanction
- That reference carries the GM's recommendation and the vetting of the FA&CAO/Budget
- (C) मांग संख्या 16 के अलग दिखाए कार्यों में, उसी योजना शीर्ष और उसी स्रोत में, एक कार्य से दूसरे कार्य में
- पीएचओडी: शून्य; मंडल रेल प्रबंधक और एसएजी: शून्य; मंडल और मुख्यालय अधिकारी: शून्य
- इसमें महाप्रबंधक का अनुमोदन और सहयोगी वित्त की सहमति चाहिए
- स्वीकृति ज्ञापन केवल बजट वीपीएन से बनता है
- (D) मांग संख्या 16 के अलग दिखाए कार्यों में, एक योजना शीर्ष से दूसरे में, या एक स्रोत से दूसरे स्रोत में
- पीएचओडी: शून्य; मंडल रेल प्रबंधक और एसएजी: शून्य; मंडल और मुख्यालय अधिकारी: शून्य
- यह स्वीकृति के लिए रेलवे बोर्ड को भेजा जाता है
- उस संदर्भ के साथ महाप्रबंधक की सिफारिश और वित्त सलाहकार एवं मुख्य लेखाधिकारी/बजट की जाँच होती है
4
ANNEXURE Eअनुलग्नक E
WHEN A RE-APPROPRIATION IS ALLOWEDपुनर्विनियोग कब चलता है
Annexure E holds the general rules that item 14 is exercised under.
- Re-appropriation is done in EXCEPTIONAL cases only
- It is done when the work losing the funds will not use them in full, or savings can be effected there
- That is judged on what is KNOWN or ANTICIPATED at the time
- Every re-appropriation is processed for the GM's or the Board's sanction by the nodal department or branch
- That is done on the recommendation of the user department or branch
- PRIOR concurrence of associate finance is required in ALL cases
- At zonal level the FA&CAO(Budget) issues the sanction memoranda through the Budget VPN, showing the changed funds position
- Every proposal carries the details in the proforma at ANNEXURE E(ii), vetted by associate finance
- Funds CANNOT be re-appropriated to a work that has no administrative approval and technical sanction of the competent authority
- The amount re-appropriated to a work shall not exceed the SANCTIONED COST of that work
- Once funds are diverted from a work it becomes the LOWEST in priority for that financial year
- Funds cannot be restored to it during the year, so temporary or reverse re-appropriation cannot be resorted to
- Since itemised works and the lumpsum provision below Rs 2.5 crore are both PINK BOOK items, re-appropriation between them is permitted
- पुनर्विनियोग केवल असाधारण मामलों में होता है
- यह तब होता है जब धन खोने वाला कार्य उसे पूरा उपयोग नहीं करेगा, या वहाँ बचत हो सकती है
- यह उस समय की ज्ञात या अनुमानित स्थिति पर तय होता है
- हर पुनर्विनियोग महाप्रबंधक या बोर्ड की स्वीकृति के लिए नोडल विभाग या शाखा तैयार करती है
- यह उपयोगकर्ता विभाग या शाखा की सिफारिश पर होता है
- सभी मामलों में सहयोगी वित्त की पूर्व सहमति आवश्यक है
- जोनल स्तर पर वित्त सलाहकार एवं मुख्य लेखाधिकारी(बजट) बजट वीपीएन से स्वीकृति ज्ञापन जारी करते हैं, बदली निधि स्थिति दिखाते हुए
- हर प्रस्ताव के साथ अनुलग्नक E(ii) के प्रपत्र का विवरण होता है, जो सहयोगी वित्त से जँचा हो
- जिस कार्य को सक्षम प्राधिकारी का प्रशासनिक अनुमोदन और तकनीकी स्वीकृति न हो, उसमें धन नहीं भेजा जा सकता
- किसी कार्य में भेजी गई राशि उस कार्य की स्वीकृत लागत से अधिक नहीं होगी
- किसी कार्य से धन हट जाने पर वह उस वित्तीय वर्ष में प्राथमिकता में सबसे नीचे आ जाता है
- वर्ष में उसे धन लौटाया नहीं जा सकता, इसलिए अस्थायी या उलटा पुनर्विनियोग नहीं किया जा सकता
- अलग दिखाए कार्य और 2.5 करोड़ रुपये से कम का एकमुश्त प्रावधान, दोनों पिंक बुक की मदें हैं, इसलिए इनके बीच पुनर्विनियोग की अनुमति है
5
ANNEXURE Eअनुलग्नक E
THE RESTRICTIONS AND THE BOARD'S LISTप्रतिबंध और बोर्ड की सूची
The same annexure sets out where re-appropriation cannot go, and what the Railway Board keeps for itself.
- THE RESTRICTIONS
- It cannot be done against the outlay during the currency of a VOTE ON ACCOUNT allotment
- It is not permissible between one GRANT, that is one demand, and another
- Nor between VOTED and CHARGED allotments
- Nor between Capital, the Railway Funds and the Railway Safety Fund
- Nor between one Railway Fund and another
- It may be done without relating it to the issue of the revised estimate or revised grant
- PRIOR APPROVAL OF THE RAILWAY BOARD
- Inter plan head re-appropriation within Demand No 16
- Re-appropriation or redistribution from, to and among Plan Head 21 Rolling Stock, for bulk order items
- To, from and among works being executed by RAIL VIKAS NIGAM LIMITED
- Portions of work constituting MATERIAL MODIFICATION above Rs 2.5 crore, where it pertains to the current year
- Any re-appropriation under the EBR allocation, such as PPP, deposit, institutional finance, market borrowings or bonds
- The outlays of priority or targeted works are not to be re-appropriated to non-priority works
- Under the same heading the annexure prints two entries that read as PERMISSIONS to the railway
- A railway may re-appropriate among Pink Book itemised works within the same plan head and allocation head, even where an outlay rises
- A railway may re-appropriate FROM Pink Book itemised works in all plan heads, if the original outlay is not reduced below Rs 1 lakh
- प्रतिबंध
- लेखानुदान के आवंटन की अवधि में परिव्यय के विरुद्ध यह नहीं हो सकता
- एक अनुदान, अर्थात् एक मांग, से दूसरी में इसकी अनुमति नहीं
- न मतदत्त और भारित आवंटनों के बीच
- न पूँजी, रेलवे निधियों और रेल संरक्षा निधि के बीच
- न एक रेलवे निधि से दूसरी में
- यह संशोधित अनुमान या संशोधित अनुदान जारी होने से जोड़े बिना किया जा सकता है
- रेलवे बोर्ड का पूर्व अनुमोदन
- मांग संख्या 16 के भीतर एक योजना शीर्ष से दूसरे में पुनर्विनियोग
- योजना शीर्ष 21 रोलिंग स्टॉक से, में और उसके भीतर पुनर्विनियोग या पुनर्वितरण, थोक आदेश की मदों के लिए
- रेल विकास निगम लिमिटेड से चल रहे कार्यों में, से और उनके बीच
- 2.5 करोड़ रुपये से ऊपर के सारगत संशोधन वाले कार्य के अंश, जहाँ वह चालू वर्ष का हो
- ईबीआर आवंटन में कोई पुनर्विनियोग, जैसे पीपीपी, जमा, संस्थागत वित्त, बाजार उधारी या बांड
- प्राथमिकता या लक्षित कार्यों का परिव्यय गैर-प्राथमिकता कार्यों में नहीं भेजा जाना है
- इसी शीर्षक के नीचे अनुलग्नक दो प्रविष्टियाँ छापता है जो रेलवे को दी गई अनुमति जैसी पढ़ी जाती हैं
- रेलवे उसी योजना शीर्ष और आवंटन शीर्ष में पिंक बुक के अलग दिखाए कार्यों के बीच पुनर्विनियोग कर सकता है, परिव्यय बढ़े तो भी
- रेलवे सभी योजना शीर्षों में पिंक बुक के अलग दिखाए कार्यों से पुनर्विनियोग कर सकता है, यदि मूल परिव्यय 1 लाख रुपये से नीचे न जाए