1
asked in 5 exams5 परीक्षाओं में पूछा गयाAEN — 4 May 2025 · AEN — 18 May 2025 · AOM — 1 June 2025 · ASTE — 4 May 2025 · ACM — 2023, 70% quota (Supplementary)
Para 620 — EARNEST MONEY AND SECURITY DEPOSITSपैरा 620 — बयाना राशि और प्रतिभूति जमा
  • (i) In WORKS contracts, a tender WITHOUT the requisite earnest money is NEVER entertained and is SUMMARILY REJECTED
  • (ii) In STORES contracts, the CONTROLLER OF STORES, with the FA&CAO, may RELAX earnest money and security deposit in specific public-interest cases
Relaxation covers unregistered firms unwilling to pay, and registered firms asked for security on items they are not registered for. EMD, now called bid security, is 2 PER CENT of the estimated cost of the work, for all works (GCC 2022, Advance Correction Slip 11 of 13.03.2026). So a works tender without EMD is rejected outright, and you should know only stores contracts may relax it.
  • (i) निर्माण अनुबंधों में आवश्यक बयाना राशि के बिना निविदा पर कभी विचार नहीं होता और वह सीधे अस्वीकार होती है
  • (ii) भंडार अनुबंधों में भंडार नियंत्रक, वित्त सलाहकार एवं मुख्य लेखा अधिकारी के साथ, जनहित के विशेष मामलों में बयाना राशि और प्रतिभूति जमा में छूट दे सकता है
छूट उन अपंजीकृत फर्मों पर है जो देने को तैयार न हों, और उन पंजीकृत फर्मों पर जिनसे अपंजीकृत मदों के लिए प्रतिभूति माँगी जाए। बयाना राशि, जिसे अब बोली प्रतिभूति कहते हैं, सभी कार्यों के लिए कार्य की अनुमानित लागत का 2 प्रतिशत है (जीसीसी 2022, अग्रिम सुधार पर्ची 11, 13.03.2026)। अर्थात् बयाना राशि के बिना निर्माण निविदा सीधे अस्वीकार होती है, और आप जानिए कि केवल भंडार अनुबंध इसमें छूट दे सकते हैं।
2
asked in 13 exams13 परीक्षाओं में पूछा गयाAEN — 18 May 2025 · AEN — 1 June 2025 · AME — 4 May 2025 · AME — 18 May 2025 · ASTE — 18 May 2025 · AEE — 2023, 70% quota (Main) · AEN — 2023, 70% quota (Supplementary) · AME — 2023, 70% quota (Supplementary) · APO — 2023, 70% quota (Supplementary) · ASTE — 2023, 70% quota (Main) · AEN — 2022, 30% LDCE quota · APO — 2022, 30% LDCE quota · ASTE — 2022, 30% LDCE quota
EMD, SD AND PERFORMANCE GUARANTEEबयाना राशि, प्रतिभूति जमा और निष्पादन गारंटी
  • EARNEST MONEY DEPOSITIt screens out non-serious firms and keeps the offer open; it is paid WITH THE TENDER in works contracts.
    • Today: 2 PER CENT of the estimated cost for ALL works, whatever the value (GCC 2022, ACS 11 of 13.03.2026)
    • Before that: 2 PER CENT up to RS 1 CRORE; beyond, RS 2 LAKH plus 0.5 PER CENT of the excess, up to RS 1 CRORE
    • Start-ups recognised by DIPP, 100 per cent Government PSUs and MSEs are EXEMPT; labour co-operatives pay 50 PER CENT
    • Refunded to unsuccessful bidders, adjusted into SECURITY DEPOSIT for the successful one
    • FORFEITED if the bidder withdraws or amends, or the successful bidder does not sign or give the PG in time
  • PERFORMANCE GUARANTEE
    • 5 PER CENT of the original contract value for works (GCC 2022, Para 16(4)); for service contracts also 5 per cent, since 24.05.2024
    • For works it is due within 21 DAYS of the LOA, or up to 60 days with 12 per cent penal interest
    • No finance concurrence is needed to RELEASE it; the Accounts Officer keeps bank guarantees in custody
  • SECURITY DEPOSIT
    • 5 PER CENT of value above RS 25 LAKH to RS 50 CRORE, up to RS 50 LAKH; above RS 50 CRORE, RS 1 CRORE
    • It guarantees faithful execution, and is forfeited on termination for the contractor's default
    The 3 PER CENT PG was a relief for tenders issued up to 31.12.2021 (Board's letter dated 20.11.2020). So the PG is 5 per cent and the bid security 2 per cent, and you should know the 3 per cent PG was a pandemic relief.
  • बयाना राशियह गैर-गंभीर फर्मों को छाँटती और प्रस्ताव खुला रखती है; निर्माण अनुबंधों में निविदा के साथ दी जाती है।
    • आज: सभी कार्यों के लिए, मूल्य कुछ भी हो, अनुमानित लागत का 2 प्रतिशत (जीसीसी 2022, एसीएस 11, 13.03.2026)
    • उससे पहले: 1 करोड़ रुपये तक 2 प्रतिशत; उससे ऊपर, 2 लाख रुपये और आधिक्य का 0.5 प्रतिशत, अधिकतम 1 करोड़ रुपये
    • डीआईपीपी से मान्य स्टार्ट-अप, 100 प्रतिशत सरकारी पीएसयू और एमएसई मुक्त हैं; श्रम सहकारी 50 प्रतिशत देती हैं
    • असफल बोलीदाताओं को लौटाई जाती है, सफल की प्रतिभूति जमा में समायोजित होती है
    • जब्त होती है यदि बोलीदाता वापस ले या बदले, या सफल बोलीदाता समय पर हस्ताक्षर या पीजी न दे
  • निष्पादन गारंटी
    • निर्माण कार्यों के लिए मूल संविदा मूल्य का 5 प्रतिशत (जीसीसी 2022, पैरा 16(4)); सेवा संविदाओं के लिए भी 24.05.2024 से 5 प्रतिशत
    • निर्माण कार्यों में यह स्वीकृति पत्र के 21 दिन के भीतर देय है, या 12 प्रतिशत दंड ब्याज के साथ 60 दिन तक
    • इसे लौटाने के लिए वित्त सहमति नहीं चाहिए; बैंक गारंटियाँ लेखा अधिकारी की अभिरक्षा में रहती हैं
  • प्रतिभूति जमा
    • 25 लाख से 50 करोड़ रुपये तक मूल्य का 5 प्रतिशत, अधिकतम 50 लाख रुपये; 50 करोड़ रुपये से ऊपर 1 करोड़ रुपये
    • यह निष्ठापूर्ण निष्पादन की गारंटी है, और ठेकेदार की चूक पर समाप्ति होने पर जब्त होती है
    3 प्रतिशत निष्पादन गारंटी 31.12.2021 तक जारी निविदाओं के लिए राहत थी (बोर्ड का 20.11.2020 का पत्र)। अर्थात् निष्पादन गारंटी 5 प्रतिशत और बोली प्रतिभूति 2 प्रतिशत है, और आप जानिए कि 3 प्रतिशत की गारंटी महामारी की राहत थी।
Report an error on this pageइस पेज में गलती बताएँ

Finished this page? Practise it now.यह पेज पूरा हुआ? अब इसका अभ्यास कीजिए।Finished this page? Practise its chapter.यह पेज पूरा हुआ? अब इसके अध्याय का अभ्यास कीजिए।

Only questions asked in real past papersकेवल पिछले वर्षों के प्रश्नपत्रों में पूछे गए प्रश्नOnly practice questions, none from a past paperकेवल अभ्यास प्रश्न, कोई भी पिछले प्रश्नपत्र से नहींPast-paper and practice questions togetherपिछले प्रश्नपत्रों के और अभ्यास प्रश्न, दोनों

or take the free Mock CBTया फ्री Mock CBT दें