1
ANNEXURE II, PART E — WORKS OUTSIDE WORKING EXPENSESअनुलग्नक II, भाग E — संचालन व्यय से बाहर के कार्य
Part E is headed 'Expenditure on works not wholly chargeable to Ordinary Working Expenses'.
- ITEMS 37 AND 38
- Including in the PRELIMINARY WORKS PROGRAMME new New Lines, Gauge Conversion, Electrification, Metro, Computerisation or PU works
- Including OTHER new works over RS 5 CRORE each
- Spending on those same classes, rolling stock or surveys NOT PROVIDED in the sanctioned budget
- ITEM 39 — OTHER WORKS NOT IN THE BUDGETThe GM may sanction unbudgeted works only within these limits, and within the lump-sum provision.
- Traffic facilities, passenger amenities, and safety works under bridges, S&T, track renewals and level crossings — LESS THAN RS 50 LAKH each
- Other works — NOT MORE THAN RS 30 LAKH each
- Machinery and plant — up to RS 10 LAKH on zones and RS 30 LAKH at PUs; in-motion weighbridges up to RS 15 LAKH, personally
- Schools, hospitals, institutes, clubs, rest houses and holiday homes — up to RS 10 LAKH each
- मद 37 और 38
- प्रारंभिक निर्माण कार्यक्रम में नई लाइनों, आमान परिवर्तन, विद्युतीकरण, मेट्रो, कंप्यूटरीकरण या उत्पादन इकाई के नए कार्य शामिल करना
- हर एक 5 करोड़ रुपये से अधिक के अन्य नए कार्य शामिल करना
- स्वीकृत बजट में प्रावधान न होने पर इन्हीं वर्गों, चल स्टॉक या सर्वेक्षणों पर खर्च
- मद 39 — बजट में न होने वाले अन्य कार्यमहाप्रबंधक बिना बजट वाले कार्य केवल इन सीमाओं में, और एकमुश्त प्रावधान के भीतर, स्वीकृत कर सकता है।
- यातायात सुविधाएँ, यात्री सुविधाएँ, और पुलों, एस एंड टी, ट्रैक नवीकरण और समपारों के संरक्षा कार्य — हर एक 50 लाख रुपये से कम
- अन्य कार्य — हर एक 30 लाख रुपये से अधिक नहीं
- मशीनरी और संयंत्र — क्षेत्रों में 10 लाख रुपये और उत्पादन इकाइयों में 30 लाख रुपये तक; चलते हुए तौल पुल 15 लाख रुपये तक, स्वयं
- स्कूल, अस्पताल, संस्थान, क्लब, विश्राम गृह और अवकाश गृह — हर एक 10 लाख रुपये तक
2
ANNEXURE II, PART E — ITEM 40, ESTIMATES AND EXCESSESअनुलग्नक II, भाग E — मद 40, प्राक्कलन और अधिकताएँ
• 40(1) — DETAILED AND REVISED ESTIMATES
- Works sanctioned in the budget at OVER RS 100 CRORE need higher sanction for their detailed or revised estimates
- An excess from ESCALATION of MORE THAN 100 PER CENT of the abstract cost needs higher sanction
- An excess for OTHER REASONS of more than 20 PER CENT or RS 20 CRORE, whichever is less, needs higher sanction
- Estimates of RS 50 TO 100 CRORE need the GM's personal approval with the FA&CAO's personal concurrence
- These are overall limits, not reset by a second revised estimate; beyond them, the Board decides
- 40(2) — MACHINERY AND PLANT
- Escalation over 50 PER CENT or RS 50 LAKH, whichever is less, needs higher sanction
- Other reasons over 10 PER CENT or RS 25 LAKH, whichever is less; material modifications over RS 10 LAKH are personal to the GM and FA&CAO
- 40(3) TO 40(5) — SURVEYS, LUMP SUMS AND PART ESTIMATES
- SURVEYS — an excess over 20 PER CENT on an estimate sanctioned higher up; budgeted surveys the GM may sanction
- LUMP-SUM WORKS — spending beyond the total lump-sum provision; thrown-forward works only if re-appropriation finds funds
- PART ESTIMATES — above 1 PER CENT of the work's budget value, for preliminaries like surveys, geo-technical studies and designs
- बजट में 100 करोड़ रुपये से अधिक पर स्वीकृत कार्यों के विस्तृत या संशोधित प्राक्कलनों को उच्च स्वीकृति चाहिए
- मूल्य वृद्धि से सार लागत के 100 प्रतिशत से अधिक की अधिकता को उच्च स्वीकृति चाहिए
- अन्य कारणों से 20 प्रतिशत या 20 करोड़ रुपये, जो भी कम हो, से अधिक की अधिकता को उच्च स्वीकृति चाहिए
- 50 से 100 करोड़ रुपये के प्राक्कलनों को वित्त सलाहकार एवं मुख्य लेखा अधिकारी की व्यक्तिगत सहमति से महाप्रबंधक का व्यक्तिगत अनुमोदन चाहिए
- ये कुल सीमाएँ हैं, दूसरे संशोधित प्राक्कलन से नहीं बदलतीं; इनसे आगे बोर्ड तय करता है
- 40(2) — मशीनरी और संयंत्र
- मूल्य वृद्धि 50 प्रतिशत या 50 लाख रुपये, जो भी कम हो, से अधिक हो तो उच्च स्वीकृति चाहिए
- अन्य कारण 10 प्रतिशत या 25 लाख रुपये, जो भी कम हो, से अधिक; 10 लाख रुपये से अधिक के महत्वपूर्ण संशोधन महाप्रबंधक और वित्त सलाहकार के व्यक्तिगत हैं
- 40(3) से 40(5) — सर्वेक्षण, एकमुश्त और आंशिक प्राक्कलन
- सर्वेक्षण — ऊपर स्वीकृत प्राक्कलन पर 20 प्रतिशत से अधिक; बजट वाले सर्वेक्षण महाप्रबंधक स्वीकृत कर सकता है
- एकमुश्त कार्य — कुल एकमुश्त प्रावधान से अधिक खर्च; आगे आए कार्य केवल तब जब पुनर्विनियोजन से धन मिले
- आंशिक प्राक्कलन — कार्य के बजट मूल्य के 1 प्रतिशत से अधिक, सर्वेक्षण, भू-तकनीकी अध्ययन और डिजाइन जैसे प्रारंभिक कामों के लिए
3
ANNEXURE IIअनुलग्नक II
MISCELLANEOUS, ITEMS 41 TO 49विविध, मद 41 से 49
The GM needs higher sanction for these.
- (41) SELLING any portion of a line, any authorised rolling stock, or any other asset costing OVER RS 3 LAKH
- (42, 43) DISMANTLING or closing an open line section; departing from contracts with branch or worked lines
- (44) Writing off irrecoverable losses over RS 1 LAKH where an employee is responsible, or RS 2 LAKH where none is
- (45) Entertaining distinguished visitors beyond RS 40,000 A YEAR
- (46) An ASSISTED SIDING, or acquiring, leasing or disposing of LAND, outside the Codes and orders
- (47) A WORKS contract over RS 100 CRORE, or a STORES contract over RS 15 CRORE
- (48) Contractors' advances: MOBILISATION over 10 PER CENT, machinery over 10 PER CENT or 75 PER CENT of its value, acceleration over 5 PER CENT or RS 5 LAKH
- (49) A MATERIAL MODIFICATION costing over RS 1.5 CRORE
- (41) लाइन का कोई भाग, कोई अधिकृत चल स्टॉक, या 3 लाख रुपये से अधिक लागत की कोई अन्य परिसंपत्ति बेचना
- (42, 43) कोई ओपन लाइन खंड उखाड़ना या बंद करना; शाखा या संचालित लाइनों के अनुबंधों से हटना
- (44) न वसूलने योग्य हानियाँ बट्टे खाते डालना, कर्मचारी उत्तरदायी हो तो 1 लाख रुपये, कोई न हो तो 2 लाख रुपये से अधिक
- (45) विशिष्ट अतिथियों के सत्कार पर वर्ष में 40,000 रुपये से अधिक
- (46) संहिताओं और आदेशों से बाहर सहायता प्राप्त साइडिंग, या भूमि का अर्जन, पट्टा या निपटान
- (47) 100 करोड़ रुपये से अधिक का निर्माण अनुबंध, या 15 करोड़ रुपये से अधिक का भंडार अनुबंध
- (48) ठेकेदारों को अग्रिम: जुटाव 10 प्रतिशत से अधिक, मशीनरी 10 प्रतिशत या उसके मूल्य के 75 प्रतिशत से अधिक, गति बढ़ाने हेतु 5 प्रतिशत या 5 लाख रुपये से अधिक
- (49) 1.5 करोड़ रुपये से अधिक लागत का महत्वपूर्ण संशोधन
4
ANNEXURE IIअनुलग्नक II
MISCELLANEOUS, ITEMS 50 TO 57विविध, मद 50 से 57
The GM needs higher sanction for these.
- (50) DIET CHARGES, except in three allowed cases
- (51) Legal proceedings against a NEWSPAPER for false and damaging articles
- (52) Supplying ELECTRICITY to outsiders, except under five conditions
- (53) Altering the existing CASH AND PAY arrangements
- (54, 55) NEW DESIGNS of goods and coaching stock, or changes to rolling stock and vessels that cut earning capacity or breach running dimensions
- (56) Altering the AUTHORISED STOCK of any description
- (57) Any expenditure on an object NOT PREVIOUSLY RECOGNISED as a fit object for railway expenditure
- DIET CHARGES ALLOWED
- Indoor patients, other than for TB, leprosy or mental disease, with basic pay up to RS 4,200
- Staff or family treated for TB, leprosy or mental disease, with basic pay up to RS 6,200
- Emergent cases of hardship, whether railway employees or not
- ELECTRICITY TO OUTSIDERS — ALL FIVE CONDITIONS
- The Electricity Act is not infringed, and there is no extra outlay, immediate or contingent
- The railway's own needs are met first, and the rates yield a PROFIT above staff rates
- The railway may cut the supply WITHOUT NOTICE OR COMPENSATION
- (50) आहार प्रभार, तीन अनुमत मामलों को छोड़कर
- (51) झूठे और हानिकारक लेखों के लिए किसी समाचार पत्र पर विधिक कार्यवाही
- (52) बाहरी पक्षों को बिजली देना, पाँच शर्तों को छोड़कर
- (53) मौजूदा नकद और वेतन व्यवस्था बदलना
- (54, 55) माल और सवारी स्टॉक के नए डिजाइन, या चल स्टॉक और जलयानों में ऐसे बदलाव जो अर्जन क्षमता घटाएँ या चालन आयाम तोड़ें
- (56) किसी भी प्रकार के अधिकृत स्टॉक में परिवर्तन
- (57) किसी ऐसे प्रयोजन पर कोई व्यय जो पहले रेल व्यय के लिए उचित प्रयोजन नहीं माना गया
- अनुमत आहार प्रभार
- टीबी, कुष्ठ या मानसिक रोग के अतिरिक्त भर्ती रोगी, जिनका मूल वेतन 4,200 रुपये तक हो
- टीबी, कुष्ठ या मानसिक रोग का उपचार पाते कर्मचारी या परिवार, मूल वेतन 6,200 रुपये तक
- कठिनाई के आपात मामले, चाहे रेल कर्मचारी हों या नहीं
- बाहरी पक्षों को बिजली — सभी पाँच शर्तें
- विद्युत अधिनियम का उल्लंघन न हो, और तत्काल या आकस्मिक कोई अतिरिक्त खर्च न हो
- रेल की अपनी आवश्यकताएँ पहले पूरी हों, और दरें कर्मचारी दरों से ऊपर लाभ दें
- रेल बिना सूचना या क्षतिपूर्ति के आपूर्ति बंद कर सके