Para 8 — GM's MEETING WITH PRINCIPAL OFFICERS FOR SELECTION OF WORKS COSTING OVER Rs.5 CRORES EACH FOR WORKS OTHER THAN TRACK RENEWALS AND Rs.1 CRORE EACH FOR TRACK RENEWALSपैरा 8 — पथ नवीकरण को छोड़ अन्य 5 करोड़ रुपये से अधिक और पथ नवीकरण के 1 करोड़ रुपये से अधिक के हर कार्य के चयन के लिए प्रधान अधिकारियों के साथ महाप्रबंधक की बैठक
- The PCE keeps a register of such works whose proposals, concurred by the FA&CAO, have come with plans
- He compiles tentative fund needs: HODs for new works, controlling departments for works in progress
- The GM meets the Principal Officers in the THIRD WEEK OF APRIL
- They select works for which the Board's approval is sought for the PWP, and finalise tentative fund needs
- The PCE convenes the meeting in consultation with the GM
- पीसीई ऐसे कार्यों का रजिस्टर रखता है जिनके वित्त सलाहकार की सहमति वाले प्रस्ताव नक्शों सहित आए हों
- वह अस्थायी निधि आवश्यकता संकलित करता है: नए कार्यों के लिए विभागाध्यक्षों से, चालू कार्यों के लिए नियंत्रक विभागों से
- महाप्रबंधक अप्रैल के तीसरे सप्ताह में प्रधान अधिकारियों से मिलते हैं
- वे पीडब्ल्यूपी के लिए बोर्ड का अनुमोदन माँगे जाने वाले कार्य चुनते हैं, और अस्थायी निधि आवश्यकता अंतिम करते हैं
- पीसीई महाप्रबंधक के परामर्श से बैठक बुलाता है
2
Para 9 — GM's MEETING WITH PRINCIPAL OFFICERS AND DRMs FOR SELECTION OF WORKS FOR INCLUSION IN P.W.Pपैरा 9 — पीडब्ल्यूपी में शामिल करने के कार्य चुनने के लिए प्रधान अधिकारियों और मंडल रेल प्रबंधकों के साथ महाप्रबंधक की बैठक
- The PCE keeps plan-head-wise lists of proposals over Rs 30 lakh concurred by the FA&CAO
- He also lists works over RS 3 CRORE approved by the Board, and the works in progress with their outlay
- Once ceilings arrive, he circulates the lists to HODs and DRMs with the ceiling limits
- His note shows each plan head's total new works, throw-forward, and any PRUNING needed to keep to the ratios
- The GM then finalises the PWP list with HODs and DRMs
- The meeting is held at least THREE WEEKS before the PWP goes to the Board
- No NEW WORK beyond the PCE's list may be proposed after that
- पीसीई वित्त सलाहकार की सहमति वाले 30 लाख रुपये से अधिक के प्रस्तावों की योजना शीर्षवार सूचियाँ रखता है
- वह बोर्ड द्वारा अनुमोदित 3 करोड़ रुपये से अधिक के कार्य, और परिव्यय सहित चालू कार्य भी सूचीबद्ध करता है
- सीमाएँ आने पर वह सूचियाँ अधिकतम सीमाओं के साथ विभागाध्यक्षों और मंडल रेल प्रबंधकों को भेजता है
- उसका नोट हर योजना शीर्ष के कुल नए कार्य, आगे जाने वाला भाग, और अनुपात में रहने के लिए आवश्यक कटौती दिखाता है
- फिर महाप्रबंधक विभागाध्यक्षों और मंडल रेल प्रबंधकों के साथ पीडब्ल्यूपी सूची अंतिम करते हैं
- बैठक पीडब्ल्यूपी बोर्ड को जाने से कम से कम तीन सप्ताह पहले होती है
- उसके बाद पीसीई की सूची से आगे कोई नया कार्य प्रस्तावित नहीं हो सकता
3
Paras 10 to 13पैरा 10 से 13
• Para 10
The PRINCIPAL CHIEF ENGINEER submits the PWP to the Board, accompanies the GM in the discussion, and submits the FWP.
- Para 11 — INSTRUCTIONS TO EACH HOD
- 11.1 The cost of the work is worked out as ACCURATELY as possible
- 11.2 Only works that have reached MATURITY, or that the Board has approved, are included
- 11.3 Approved schemes are not altered without very STRONG circumstances
- 11.4 Works with a COMMON OBJECTIVE are justified as one scheme; across railways, by a JOINT estimate
- 11.4 The railway with the major portion gathers the other railways' figures
- 11.5 Capacity and operating improvement works carry a financial justification wherever possible
- 11.5 If not, and the work is inescapable, a CHEAPER ALTERNATIVE is examined first
- 11.5 Otherwise, full notes with the FA&CAO's comments explain going ahead though not remunerative
- 11.6 FINANCIALLY REMUNERATIVE works give a return of NOT LESS THAN 12% by the DCF method
- 11.7 A dropped work proposed again carries FRESH cost justification, citing past programmes and why it was dropped
- TWO READINGS OF THE RATE OF RETURN
- The circular sets 12% by DCF
- The departmental notes say a work needs a minimum return of 10% under DCF to be financially acceptable
- Para 12After the PWP, the PCE issues the booklet to divisions and HODs.
- Para 13
- The division's Works Branch compiles a DIVISIONAL WORKS PROGRAMME of works up to Rs 5 lakh, issued by 31 DECEMBER
- It shows, plan-head-wise, works in progress and new works, in form 2108-E
- Its totals must tally with the FWP
- Divisions complete such works within the FINANCIAL YEAR, with no throw forward
- पैरा 11 — हर विभागाध्यक्ष के लिए निर्देश
- 11.1 कार्य की लागत यथासंभव सटीक निकाली जाती है
- 11.2 केवल परिपक्व हो चुके, या बोर्ड द्वारा अनुमोदित, कार्य शामिल किए जाते हैं
- 11.3 अनुमोदित योजनाएँ बहुत प्रबल परिस्थितियों के बिना नहीं बदली जातीं
- 11.4 समान उद्देश्य वाले कार्यों का औचित्य एक योजना के रूप में; कई रेलों में, संयुक्त अनुमान से
- 11.4 मुख्य भाग वाली रेल अन्य रेलों के आँकड़े एकत्र करती है
- 11.5 क्षमता और संचालन सुधार कार्यों का, जहाँ संभव हो, वित्तीय औचित्य होता है
- 11.5 यदि नहीं, और कार्य अपरिहार्य हो, तो पहले सस्ता विकल्प देखा जाता है
- 11.5 अन्यथा, वित्त सलाहकार की टिप्पणियों सहित पूरे नोट बताते हैं कि लाभकारी न होने पर भी आगे क्यों बढ़ें
- 11.6 वित्तीय रूप से लाभकारी कार्य डीसीएफ पद्धति से 12% से कम प्रतिफल नहीं देते
- 11.7 छोड़ा गया कार्य फिर प्रस्तावित हो, तो पिछले कार्यक्रमों और छोड़ने के कारण बताते हुए नया लागत औचित्य होता है
- प्रतिफल दर के दो पाठ
- परिपत्र डीसीएफ से 12% तय करता है
- विभागीय नोट्स कहते हैं कि वित्तीय रूप से स्वीकार्य होने के लिए कार्य को डीसीएफ के अंतर्गत न्यूनतम 10% प्रतिफल चाहिए
- पैरा 12पीडब्ल्यूपी के बाद पीसीई मंडलों और विभागाध्यक्षों को पुस्तिका जारी करता है।
- पैरा 13
- मंडल की निर्माण शाखा 5 लाख रुपये तक के कार्यों का मंडल निर्माण कार्यक्रम संकलित कर 31 दिसंबर तक जारी करती है
- यह योजना शीर्षवार चालू कार्य और नए कार्य, प्रपत्र 2108-E में, दिखाता है
- इसके योग एफडब्ल्यूपी से मिलने चाहिए
- मंडल ऐसे कार्य वित्तीय वर्ष में ही, बिना आगे ले जाए, पूरे करते हैं
4
Para 14 — TIME TABLEपैरा 14 — समय सारणी
Everyone acts by the time table in Appendix VIII; its dates are the LATEST, and proposals should move earlier in stages.
Most of the appendix is printed out of line; these rows are clear.
- Submission of the PWP: FIRST WEEK OF SEPTEMBER, by the date the Board fixes
- List of new works up to RS 2 LAKH issued by the CE to DRMs and HODs: 30 SEPTEMBER
- Discussion of the PWP with the Board by the GM: OCTOBER or NOVEMBER
- Submission of the FWP: NOVEMBER, within a fortnight of the minutes
- Divisional Works Programme for works up to Rs 5 lakh: 31 DECEMBER
- Issue of the PINK BOOK: THIRD WEEK OF FEBRUARY, after the budget is presented
- पीडब्ल्यूपी की प्रस्तुति: सितंबर का पहला सप्ताह, बोर्ड की तय तिथि तक
- सीई द्वारा मंडल रेल प्रबंधकों और विभागाध्यक्षों को 2 लाख रुपये तक के नए कार्यों की सूची: 30 सितंबर
- महाप्रबंधक द्वारा बोर्ड के साथ पीडब्ल्यूपी पर चर्चा: अक्टूबर या नवंबर
- एफडब्ल्यूपी की प्रस्तुति: नवंबर, कार्यवृत्त के एक पखवाड़े में
- 5 लाख रुपये तक के कार्यों का मंडल निर्माण कार्यक्रम: 31 दिसंबर
- पिंक बुक जारी करना: फरवरी का तीसरा सप्ताह, बजट प्रस्तुत होने के बाद